Yesterday the blocks came, so they started building seriously. Of course, then it started raining so they had to stop. Since we need rain, we're happy anyway.
Friday, October 30, 2009
Wednesday, October 28, 2009
Up, Up, Up
Tommorow hopefully they will start building the second floor. They prepared the wood and metal for the stairs. Again, tommorow hopefully they'll pour the concrete.
Monday, October 26, 2009
More and more mess....
We can now throw pots of boiling oil on the enemy soldiers attacking our house: The playroom is finished (or at least finished being demolished):
They took down the kitchen -
The guest bathroom with a new door:
Powder bathroom: The kitchen:
The took down the wall between the old kitchen and the mirpesset sherut-
Form the other side of the mirpesset they took down the window but they still need to take down the wall-
They took down the old dividing wall between the kitchen and living room-
Sunday, October 25, 2009
There's a hole in our house.....
So today, they started the day by taking down the dry wall room.
They ended the day by turning our house into swiss cheese.
They put the stuff they took down in the "mamad".
Friday, October 16, 2009
We can now have a succah
as soon as they put filler and they put tiles and we move in and we get a succah......
The kablan said that today they'll take off the wood.
Thursday, October 15, 2009
A pump
So we didn't stay for the pouring of our cement floor, but we got to see the pump and cement trucks (9 trucks) while they were pouring a floor for a neighbor:
We comply with requests
The big cement pouring will happen at 2 o'clock, so stay tuned.
We were asked to post pre-building pictures, so we will comply:
Wednesday, October 14, 2009
This is not a blog
This is just a way of telling facts without a telephone. There will be no funny jokes, humorous content or anything original.
Yesterday the kablan dug up our backyard and prepared for pouring the cement tommorow (hopefully).
View from our living room door: